Month: December 2012
-
Tile…And Some Marble
Below are some photos of the new (and not yet cleaned) tile work at the Lesmeister Guesthouse. There’s also a nice marble threshold installed where the…
Learn More -
Julia Dean Floors Going Down
The wood floors are going down in the Julia Dean apartment. They have also finished the tile floor in the bathroom and utility room, but…
Learn More -
Tile and Kitchen Cabinetry in Julia Dean
The Julia Dean apartment in the Lesmeister Guesthouse has gotten ahead of the Laurel apartment lately. Laurel finally got gray primer on its metal ceiling…
Learn More -
First Party Held At Lesmeister Guesthouse
Yesterday evening a small group of us gathered in the Julia Dean apartment of the Lesmeister Guesthouse for a little after-work get-together. Joining me for a little…
Learn More -
Getting Ready For Tile!
The first photo below shows the beefy support for the bathroom vanity they’re building for the Julia Dean apartment. This is the handicapped accessible unit,…
Learn More -
Building The Stair Rails
The welder has started work in the Lesmeister Guesthouse Laurel apartment, building the steel rails for the stairs that lead up from the main level…
Learn More -
Goodbye Stone Columns
Architect Tommy Jameson was at the Lesmeister Guesthouse project today, and among decisions made was one to eliminate the seven stone support columns for the…
Learn More -
Lesmeister’s First Christmas
Pocahontas had its annual Christmas parade downtown Thursday evening, and I turned the (temporary) lights on inside the building so people could look through the…
Learn More