Lesmeister Guesthouse
Blog entries pertaining to The Lesmeister Guesthouse.
-
Both Front Doors Installed
Both Lesmeister Guesthouse front doors are now installed, and they have cut holes in them and installed temporary locks, so there’s no turning back now!…
Learn More -
A Front Door Appears
One of the two Lesmeister Guesthouse front doors appeared today (see below), with overhead glass transom. They are beautiful, custom-made solid wood doors but must…
Learn More -
Drywall Going Up, Deck Footing Going In
Today there’s fresh concrete behind the Lesmeister Building as the workers poured some of the footing to support the building’s rear deck. (photo below) Also,…
Learn More -
Windows In (and doors not)
All six rear windows are now installed in the Lesmeister building (see “before” and “now” photos below), and it sure looks good to see them.…
Learn More -
An Important Milestore: Insulation
They insulated all the exterior walls of the Lesmeister apartments today. This means they can soon start hanging drywall (Sheetrock)! They insulated with high-density foam they…
Learn More -
First Window. About time!
I’ve seen so many new houses being built. One week to put in the footings and foundations. One week to frame it. By the third…
Learn More -
The Old Storefront…coming to life again
Architect Tommy Jameson studied the bones of the old Lesmeister building and designed a restoration of the building’s storefronts that he believes closely matches what…
Learn More -
Lesmeister Front Sidewalk
Below is a photo of the new sidewalk in front of the Lesmeister Guesthouse. They put 45 degree joints around the support columns so if a…
Learn More